Timeline told on Port of Port Angeles’ Maritime Trade Center

Construction slated to begin this May

PORT ANGELES — The Port of Port Angeles is entering Phase 2 of development of the Maritime Trade Center on the former PenPly/KPly site, with bidding scheduled to open March 26, according to Director of Engineering Chris Hartman.

Hartman spoke to commissioners Connie Beauvais and Steve Burke at the port’s Tuesday meeting. Commissioner Coleen McAleer had an excused absence.

Construction is anticipated to begin in May and be completed by December, Hartman said.

The scope of work on the 18-acre site includes grading; construction of new water and sewer mains; construction of a stormwater collection, conveyance and treatment facility; and installation of a new asphalt access road.

The port allocated $10.232 million in its 2024 capital budget for the project; it will pay $3.5 million of the cost, with $6.732 million coming from a U.S. Department of Commerce Economic Development Administration grant.

“It has the potential of being developed into five separate lease blocks throughout the site,” Hartman said. “Outside of that, there’s some general laydown and other boat repair areas.”

The port chose to focus on building out infrastructure, with particular attention to stormwater management, when it had to scale back the original design to meet its budget, Hartman said. The port received a total grant amount of $11.034 million.

“The original cost estimates were done in 2019, and we got awarded the grant in 2022,” Hartman said. “Now that we’re going into construction in 2024, all of those prices have just continued to far outpace traditional yearly escalations.”

The price to complete the project as originally planned would be about $18 million, he said.

Among the cost savings were shortening a road on the site so it accesses just three of the five lease lots, and replacing a good deal of proposed asphalt surfacing with crushed rock.

“What would be the ramifications of truck traffic where it’s unpaved, like going over the cargo area?” Beauvais asked. “Are you taking into consideration what that would do to the stormwater infrastructure?”

Hartman said that concern would likely need to be addressed at some point.

“If you had a bunch of heavy haul on the gravel site and then onto pavement, you’re going to track out a lot of sediment that gets washed into the storm drains,” he said. “If there was a specific cargo [like chips] that was being considered, you might have to come in back in and do additional paving.”

The port is still in the process of talking to businesses and gauging interest in the site, so it wanted to remain open to ideas about layout and not get ahead of what individual clients might need, Executive Director Paul Jarkiewicz said.

“It leaves us a lot of flexibility to do a number of different things,” Jarkiewicz said. “We want to remain flexible and make the site operative so a tenant can build itself or the port can build to suit.”

The port has been able to realize cost savings by doing some of the work itself, such as removing and breaking up old concrete foundations on the site.

“The more of that we can do, the more we’re going to save,” facilities maintenance supervisor Wilson Easton said.

Easton said port staff found “logs galore” left over from a state Department of Ecology dredging project in 2014 during which 53,765 tons of contaminated soil had been excavated and removed. Some of the logs could be chipped, he said, while others soaked with creosote would have to be taken to a transfer station.

Port commissioners unanimously approved the $50,000 purchase of a pre-fabricated 40-foot by 72-foot pole building kit that facilities maintenance will for use for equipment storage. Facilities maintenance staff will construct the building.

________

Reporter Paula Hunt can be reached at paula.hunt@peninsuladailynews.com.

More in News

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Sunday at the Sol Duc trailhead in Olympic National Park. (National Park Service)
National Park Service asks for help in locating missing woman

Rented vehicle located Sunday at Sol Duc trailhead

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror as Jayne Johnson of Sequim tries on a skirt during a craft fair on Saturday in Uptown Port Townsend. (Steve Mullensky/for Peninsula Daily News)
Mirror image

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror… Continue reading

Flu cases rising on Peninsula

COVID-19, RSV low, health official says

Clallam board approves levy amounts for taxing districts

Board hears requests for federal funding, report on weed control

Jury selected in trial for attempted murder

Man allegedly shot car with 2 people inside

The Festival of Trees event raised a record $181,000 through the Olympic Medical Center Foundation during Thanksgiving weekend events. (Dave Logan/for Peninsula Daily News)
Festival of Trees nets record-setting $181K

Dr. Mark Fischer honored with Littlejohn Award for contributions to healthcare

Matthew Nash/Olympic Peninsula News Group
Four locations are accepting items for children ages 1-18 for Toys for Sequim Kids set for Dec. 16 at the Sequim Prairie Grange. Locations include Anytime Fitness Sequim, Co-Op Farm and Garden, Sequim Electronics (Radio Shack) and the YMCA of Sequim.
Toys for Sequim Kids seeks donations for annual event

Trees are up for Toys for Sequim Kids, an annual… Continue reading

The 34-foot tree aglow with nearly 20,000 lights will adorn downtown Port Angeles throughout the holiday season. (Dave Logan/For Peninsula Daily News)
O Christmas Tree

Tree lighting in downtown Port Angeles

Sequim administrative staff members said they look to bringing city shop staff, including water, streets and stormwater, back under one roof with site improvements. In an effort to find the funds to do so, they’ve paused $350,000 in funding originally set for a second-floor remodel of the Sequim Civic Center and designated it for the shop area. (Matthew Nash/Olympic Peninsula News Group)
Sequim Civic Center remodel on hold for city shop upgrades

Public Works director says plan would be less than $35M

Emily Westcott shares a story in the Sequim City Council chambers on Nov. 10 about volunteering to clean up yards. She was honored with a proclamation by the council for her decades of efforts. (Matthew Nash/Olympic Peninsula News Group)
Westcott honored for community service

Volunteer recognized with proclamation for continued efforts