Pricetag for Port Angeles waterfront plan soars

PORT ANGELES — City Hall will have to spend an additional $700,000 to finish a portion of its Waterfront and Transportation Improvement Plan, after a contract came in at more than $1.2 million.

The total cost of creating the plan is now at about $1.7 million.

Following staff direction, the Port Angeles City Council on Tuesday night unanimously approved spending the additional funds to pay for the construction drawings needed to implement about half of the waterfront redevelopment aspect of the project.

The drawings, which include engineering and planning documents, are the main part of the second contract for the project with Studio Cascade of Spokane.

That contract came in at nearly $1.253 million, over four times higher than initially anticipated in August, and $700,000 over what the city had budgeted for the project this year.

The first contract with Studio Cascade, which involved about a half-dozen subconsultants, cost $484,000.

It included designing the waterfront improvements, new entryway and directional signs, and starting a citywide transportation plan.

When the city began working on it more than six months ago, the plan was anticipated to cost around $778,000 to develop.

The additional money would likely come from the city’s economic development fund, said Nathan West, city economic and community development director.

Several council members, noting the need to improve the waterfront and community support for the project, voiced support for spending the additional money.

“The community is behind this project,” said Mayor Dan Di Guilio.

“I think we as a council have a responsibility to do what we can to make this happen.”

Council member Brad Collins questioned whether the economic development fund should be used. He said the fund should be used to create jobs.

Other council members disagreed.

“It will create jobs; it will revitalize downtown,” said Deputy Mayor Don Perry.

West said the price tag increased so dramatically because the scope of the waterfront plan changed during the public input process.

Initially, it was mainly going to be limited to the west end of downtown, West said, but was expanded in response to comments from the public to include other areas, such as City Pier and Hollywood Beach. A west end beach was also added to the design.

“They [public] have a lot of interest in getting a variety of improvements on the waterfront that perhaps weren’t anticipated,” West said, adding, “we’re happy with the direction that we’re moving in.”

The waterfront plan is estimated to cost $17.3 million to fully implement.

Acknowledging that the plan is too much for the city to chew, at least in one sitting, the council also Tuesday directed Studio Cascade and its subconsultants to draft only construction drawings, including engineering and permitting documents, for the west half of the waterfront project.

That move reduced the cost of the second contract by about $1.1 million.

The west half includes a boardwalk west of the ferry terminals, new park on the east side of the Valley Creek estuary, and landscaping and road improvements along the west half of Railroad Avenue. All together, those improvements are estimated to cost $7 million.

What’s left out: improvements to City Pier, Laurel Street and the other half of Railroad Avenue, and expansion of Hollywood Beach.

West said he still hopes to begin work on the waterfront sometime this year.

But he acknowledged before the meeting that grant funding has dried up in the last few years, and the city may have to throw up some cash to get it started.

West said his staff has not had the time yet to pursue any grants, but added, “I’m not ready to rule it [grant funding] out as an option.”

City Manager Kent Myers told the council that the city is seeking funding through the U.S. Economic Development Administration.

West said Victoria Express, which wants to move to what would be a new waterfront park, may also help with the new improvements.

The city has estimated that city funds will make up 20 percent of the waterfront project’s cost.

The first six of the 62 new directional signs planned as part of the plan will be installed next month. The rest will be installed throughout the year.

The design of two new entryway monuments, controversial because one would be located at the bottom of the Morse Creek S-curve, remain on hold.

The transportation plan will be done by 2013, said Roberta Korcz, city assistant planner.

For more information on the waterfront project, visit www.pa-waterfront.org/intro.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Sunday at the Sol Duc trailhead in Olympic National Park. (National Park Service)
National Park Service asks for help in locating missing woman

Rented vehicle located Sunday at Sol Duc trailhead

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror as Jayne Johnson of Sequim tries on a skirt during a craft fair on Saturday in Uptown Port Townsend. (Steve Mullensky/for Peninsula Daily News)
Mirror image

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror… Continue reading

Flu cases rising on Peninsula

COVID-19, RSV low, health official says

Clallam board approves levy amounts for taxing districts

Board hears requests for federal funding, report on weed control

Jury selected in trial for attempted murder

Man allegedly shot car with 2 people inside