Port of Port Angeles delays its Maritime Trade Center design

Projected cost of 16,000-square-foot building over budget

PORT ANGELES — The Port of Port Angeles is stepping back for at least one year from pursuing a design of its Marine Trade Center project due to an unexpectedly high construction cost estimate.

Port staff recommended that port officials pause to look into additional funding sources to bring the project cost down.

“Staff does not recommend we continue with future phases of design until we can come up with a business case that would support the construction of the building,” Chris Hartman, director of engineering, told port commissioners on Tuesday.

The Marine Trade Center is envisioned as an industrial building capable of housing 175-foot vessels and the equipment necessary to haul these vessels out of the water for maintenance and repair.

The center also would house a multitude of marine trades as part of the Port of Port Angeles’ effort to expand maritime commerce.

The building would be constructed with pre-engineered steel with a single pitched roof while allowing space for a similar structure to be built in the future.

Port officials hired Carletti Architects as consultants to develop a design and associated construction cost estimate.

“We went in with a target construction cost budget of about $4 million as we worked with the consultants and we quickly learned that our idea of having a 30,000-square-foot building was not in the cards so we shrunk that down to about 16,000 square feet, designed in a way that it could be expanded to double that size in the future,” Hartman said.

Even after reducing the size, the estimated construction cost was $10.25 million, more than double the budget.

“So we went back to the consultant and asked for some engineering ideas of what could be removed to simplify and reduce the cost of the facility,” Hartman told commissioners.

“There’s a long list of items that we could remove. That cost estimate came back at $8.75 million,” he said.

Inflation and supply chain issues brought on by the COVID-19 pandemic and other national and international situations have played a significant role in the high cost, he added.

“There are numerous factors that have played a role in the increased cost estimates. There has been a 25 percent increase in construction costs across the state. Material supply chain impacts, supply and demand for federal and state funding, and shortage of available contractors are all drivers of this cost increase,” Hartman said.

In stepping back, port officials will look at state and federal funding opportunities that could close the gap in the budget and estimated costs.

That search may take a year or more.

“We’re going to be searching high and wide for any available funding programs and opportunities,” Hartman said.

“There has been an influx of federal funds from the infrastructure benefit bills that have passed recently, and we have been working really diligently on finding and applying for those.”

________

Reporter Ken Park can be reached at kpark@peninsuladailynews.com.

More in News

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Sunday at the Sol Duc trailhead in Olympic National Park. (National Park Service)
National Park Service asks for help in locating missing woman

Rented vehicle located Sunday at Sol Duc trailhead

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror as Jayne Johnson of Sequim tries on a skirt during a craft fair on Saturday in Uptown Port Townsend. (Steve Mullensky/for Peninsula Daily News)
Mirror image

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror… Continue reading

Flu cases rising on Peninsula

COVID-19, RSV low, health official says

Clallam board approves levy amounts for taxing districts

Board hears requests for federal funding, report on weed control

Jury selected in trial for attempted murder

Man allegedly shot car with 2 people inside

The Festival of Trees event raised a record $181,000 through the Olympic Medical Center Foundation during Thanksgiving weekend events. (Dave Logan/for Peninsula Daily News)
Festival of Trees nets record-setting $181K

Dr. Mark Fischer honored with Littlejohn Award for contributions to healthcare

Matthew Nash/Olympic Peninsula News Group
Four locations are accepting items for children ages 1-18 for Toys for Sequim Kids set for Dec. 16 at the Sequim Prairie Grange. Locations include Anytime Fitness Sequim, Co-Op Farm and Garden, Sequim Electronics (Radio Shack) and the YMCA of Sequim.
Toys for Sequim Kids seeks donations for annual event

Trees are up for Toys for Sequim Kids, an annual… Continue reading

The 34-foot tree aglow with nearly 20,000 lights will adorn downtown Port Angeles throughout the holiday season. (Dave Logan/For Peninsula Daily News)
O Christmas Tree

Tree lighting in downtown Port Angeles

Sequim administrative staff members said they look to bringing city shop staff, including water, streets and stormwater, back under one roof with site improvements. In an effort to find the funds to do so, they’ve paused $350,000 in funding originally set for a second-floor remodel of the Sequim Civic Center and designated it for the shop area. (Matthew Nash/Olympic Peninsula News Group)
Sequim Civic Center remodel on hold for city shop upgrades

Public Works director says plan would be less than $35M

Emily Westcott shares a story in the Sequim City Council chambers on Nov. 10 about volunteering to clean up yards. She was honored with a proclamation by the council for her decades of efforts. (Matthew Nash/Olympic Peninsula News Group)
Westcott honored for community service

Volunteer recognized with proclamation for continued efforts