Examiner approves Habitat project

Wetland buffer limits size to 45 units

SEQUIM — Habitat for Humanity of Clallam County’s Sequim Avenue Development townhome project has been approved by the Sequim’s hearing examiner.

Peregrin Sorter with Laminar Law shared his decision on June 6 with various conditions requested by the Sequim city staff.

Per city code, the public has until Friday to appeal his decision for the conditional use permit and binding site plan.

Habitat’s development calls for 45 units, including a combination of fourplex, triplex and duplex townhomes at the south intersection of South Sequim Avenue and East Brownfield Road.

Colleen Robinson, CEO of Habitat for Humanity, said they don’t plan to appeal any of the conditions.

At a May 22 public hearing at the Sequim Civic Center, Robinson said her agency is looking for “permanent affordability” using a land-lease model where homeowners own the structure above ground and Habitat retains the land; if homes go on the market, they must be sold to residents at or below 80 percent of the area median income.

According to city documents, staff wrote that the “proposed development would serve the public interest by adding much needed housing options to the local market, helping to address the community’s housing demand … (and) this housing option would bring more available housing to the city at a time when housing is scarce.”

Robinson said approval of a building permit could take up to six months if the binding site plan and conditional use permits go through. She previously said the “best-case timeline” would be to start building homes in mid-2027.

Wetland

While Sorter approved the project for 48 homes, Robinson said they will build 45 homes to avoid building near a 1-acre wetland on the site.

City staff wrote that the buffer for the wetland would be 25 feet with a 15-foot setback, but because the wetland was altered by agricultural activities and maintained as a pasture, disrupting its natural features, the setback can be reduced so long as Habitat enhances it.

According to city documents, two triplexes and a playground would slightly go into the setback, but Habitat officials plan to remove invasive species and plant native vegetation.

Entrance

Due to Habitat’s project and neighboring Bell Creek Estates Subdivision’s entrances being less than 125 feet apart on South Sequim Avenue, city staff will require Habitat officials to either redesign their entrance or work with an engineer to write a request to the city on why the deviation is needed.

Nick Dostie, Sequim’s city engineer and deputy director of public works, said he is willing to work with Habitat officials on either plan and doesn’t foresee an issue with either option.

Robinson said they don’t plan to redesign the project’s entrance and they’ll work with an engineer.

Fences, walls

Following a concern from a neighbor, a fence will be required along the development’s eastern side to protect residents from an electric fence.

A proposed retaining wall on the southern boundary of the development will be designed and engineered by a licensed professional to account for surcharge load considerations, according to city documents, and prior to a site construction permit issuance, the retaining wall design must be submitted for review and approved by city staff to ensure it is compliant with applicable engineering and safety standards.

As one of the conditions for the binding site plan, Habitat must keep at least 43 feet between the property line and its structures on the south side of its property. At the public hearing, neighbors shared concern about the development infringing on their properties. Habitat’s consultant said that would not happen.

Community

Per city documents, the development will create 407 total average weekday, daily vehicle trips with no mitigation required.

At the hearing, city staff said a Six-Year Transportation Improvement Plan addresses concerns for Habitat and Bell Creek Subdivision’s impact on the South Sequim Avenue/U.S. Highway 101 eastbound left-turn intersection and that Habitat’s project would not make the intersection worse in the meantime.

According to city documents, Habitat’s project would provide two off-street parking spaces per unit and an additional 26 on-street parking stalls proposed on the northern and western portions of the city.

Despite objections from Habitat officials at the public hearing about the word “shall” due to its perceived subjectivity, Sorter kept verbiage the same for shared driveways.

His decision reads, “duplex and fourplex units shall consider utilizing shared driveways where feasible to minimize curb cuts and reduce potential traffic conflicts. Driveway access shall be designed to limit the number of curb cuts along the internal roadway while ensuring safe and functional access for all units.”

Sorter also is requiring a professional cultural resource survey before any land disturbance with written notification to the Jamestown S’Klallam Tribal Historic Preservation Office at least five business days before starting any archaeological survey, fieldwork or ground-disturbing activities.

According to city documents, staff “determined that (Habitat’s) proposal would meet all applicable concurrency requirements and that there are adequate public utilities and services to serve the proposed development.”

They write that it would not generate noise, glare or odors beyond that of a typical residential use.

Along with the Sequim Avenue Development, Habitat continues engineering work on its Lyon’s Landing project in Carlsborg.

For more information about Habitat projects, visit habitatclallam.org.

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. He can be reached by email at matthew.nash@sequimgazette.com.

More in News

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Sunday at the Sol Duc trailhead in Olympic National Park. (National Park Service)
National Park Service asks for help in locating missing woman

Rented vehicle located Sunday at Sol Duc trailhead

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror as Jayne Johnson of Sequim tries on a skirt during a craft fair on Saturday in Uptown Port Townsend. (Steve Mullensky/for Peninsula Daily News)
Mirror image

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror… Continue reading

Flu cases rising on Peninsula

COVID-19, RSV low, health official says

Clallam board approves levy amounts for taxing districts

Board hears requests for federal funding, report on weed control

Jury selected in trial for attempted murder

Man allegedly shot car with 2 people inside

The Festival of Trees event raised a record $181,000 through the Olympic Medical Center Foundation during Thanksgiving weekend events. (Dave Logan/for Peninsula Daily News)
Festival of Trees nets record-setting $181K

Dr. Mark Fischer honored with Littlejohn Award for contributions to healthcare

Matthew Nash/Olympic Peninsula News Group
Four locations are accepting items for children ages 1-18 for Toys for Sequim Kids set for Dec. 16 at the Sequim Prairie Grange. Locations include Anytime Fitness Sequim, Co-Op Farm and Garden, Sequim Electronics (Radio Shack) and the YMCA of Sequim.
Toys for Sequim Kids seeks donations for annual event

Trees are up for Toys for Sequim Kids, an annual… Continue reading

The 34-foot tree aglow with nearly 20,000 lights will adorn downtown Port Angeles throughout the holiday season. (Dave Logan/For Peninsula Daily News)
O Christmas Tree

Tree lighting in downtown Port Angeles

Sequim administrative staff members said they look to bringing city shop staff, including water, streets and stormwater, back under one roof with site improvements. In an effort to find the funds to do so, they’ve paused $350,000 in funding originally set for a second-floor remodel of the Sequim Civic Center and designated it for the shop area. (Matthew Nash/Olympic Peninsula News Group)
Sequim Civic Center remodel on hold for city shop upgrades

Public Works director says plan would be less than $35M

Emily Westcott shares a story in the Sequim City Council chambers on Nov. 10 about volunteering to clean up yards. She was honored with a proclamation by the council for her decades of efforts. (Matthew Nash/Olympic Peninsula News Group)
Westcott honored for community service

Volunteer recognized with proclamation for continued efforts