As Clallam County Courthouse renovation winds down, third change order requested

PORT ANGELES — As renovations to the historic Clallam County Courthouse wrap up later this week, public works officials are asking for a final change order to a $347,388 contract with Advanced Construction Inc.

The $13,543 change order — the third since construction began late last year — will pay for additional rubber base, roofing, wood trim, molding, bird spikes and other items.

It also returns $3,263 for masonry that was not installed.

“Most of these items, the bigger items, were unforeseen,” Joel Winborn told the three county commissioners Monday.

Winborn is county parks, fair and facilities manager.

‘Missed in drawings’

“A couple of the things were things we just missed in the drawings,” he said.

Commissioner Steve Tharinger, who is also a state legislator, took part in Monday’s county work session by speakerphone from Olympia.

The main floor of the older wing of the courthouse was painted and remodeled. Exterior work included a new staircase for the west entrance and repairs to the clock

and bell tower.

“We’re scheduled to complete this project Thursday, and that includes the final cleaning and everything,” Winborn said.

The second and third floors of the historic courthouse were remodeled in 1999. A fuel-burning boiler was replaced with an energy-efficient electric steam boiler in 2009.

If the commissioners approve the change order today, the total cost of the project will be $360,930.

Half of the project was paid for by a 50-50 matching grant from the state Department of Archaeology and Historic Preservation.

Clallam County budgeted its share through its capital projects fund.

Built in 1914, the historic courthouse made the National Register of Historic Places in 1987.

The larger east side of the courthouse and its connecting jail were built in 1979.

Mukilteo-based Advanced Construction was selected because it submitted the lowest of four bids the county received last September.

‘Fantastic job’

“They’re doing a fantastic job,” Winborn said. “It’s just time to get them out and clean it up.”

Four county departments were temporarily relocated during construction: Washington State University Extension, the law library, environmental health and the Parks, Fair and Facilities Division.

In other discussion from Monday, County Engineer Ross Tyler told commissioners that Priest Road northeast of central Sequim will be closed for up to one week sometime between

March 15 and March 31.

The closure is needed to replace an irrigation ditch crossing. A new culvert will be installed, and humps in the road will be removed.

The irrigation ditch is four-tenths of a mile north of Washington Street.

Commissioner Mike Doherty recommended that road crews post signs during the closure that show alternate routes.

Tyler said the work will likely be finished in less than seven days.

“It’s just in the best interest of the public to be prepared for the worst-case scenario,” he said.

In other news, the county has applied for a grant renewal with the state Department of Ecology for a community litter cleanup program.

The $61,673 grant, which runs through June 2013, would pay for two Clallam County chain gang supervisors and administration costs.

Jail Superintendent Ron Sukert said the county has been successful in securing the grant “because we do well with the monies that we’ve given.”

Reporter Rob Ollikainen can be reached at 360-417-3537 or at rob.ollikainen@peninsuladailynews.com.

More in News

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on Saturday at the Airport Garden Center in Port Angeles. All proceeds from the event were donated to the Peninsula Friends of Animals. (Dave Logan/for Peninsula Daily News)
Santa Paws

Christopher Thomsen, portraying Santa Claus, holds a corgi mix named Lizzie on… Continue reading

Peninsula lawmakers await budget

Gov. Ferguson to release supplemental plan this month

Clallam County looks to pass deficit budget

Agency sees about 7 percent rise over 2025 in expenditures

Officer testifies bullet lodged in car’s pillar

Witness says she heard gunfire at Port Angeles park

A copper rockfish caught as part of a state Department of Fish and Wildlife study in 2017. The distended eyes resulted from a pressure change as the fish was pulled up from a depth of 250 feet. (David B. Williams)
Author to highlight history of Puget Sound

Talk at PT Library to cover naming, battles, tribes

Vern Frykholm, who has made more than 500 appearances as George Washington since 2012, visits with Dave Spencer. Frykholm and 10 members of the New Dungeness Chapter, NSDAR, visited with about 30 veterans on Nov. 8, just ahead of Veterans Day. (New Dungeness Chapter DAR)
New Dungeness DAR visits veterans at senior facilities

Members of the New Dungeness Chapter, National Society Daughters of… Continue reading

Festival of Trees contest.
Contest: Vote for your favorite tree online

Olympic Medical Center Foundation’s Festival of Trees event goes through Dec. 25

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Sunday at the Sol Duc trailhead in Olympic National Park. (National Park Service)
National Park Service asks for help in locating missing woman

Rented vehicle located Sunday at Sol Duc trailhead

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror as Jayne Johnson of Sequim tries on a skirt during a craft fair on Saturday in Uptown Port Townsend. (Steve Mullensky/for Peninsula Daily News)
Mirror image

Kendra Russo of Found and Foraged Fibers in Anacortes holds a mirror… Continue reading

Flu cases rising on Peninsula

COVID-19, RSV low, health official says

Clallam board approves levy amounts for taxing districts

Board hears requests for federal funding, report on weed control

Jury selected in trial for attempted murder

Man allegedly shot car with 2 people inside